no need for sea link, national grid excessive costs not needed, just upgrade,

The £3.2 Billion Electricity Bill

WE Don’t Need to Pay

National Grid says its Sea Link undersea cable is essential. We say the evidence doesn't support that and there are far cheaper options that do the same job with far less damage.

Sea Link was approved. The case for it still doesn’t hold up.

The case National Grid put forward is weaker now than when it started. Below we explain why, and what happens next.

The original reason has largely gone

Sea Link was originally justified as the way to move up to 2,000 MW of power out of the Sizewell area in Suffolk. That need has shrunk to just 352 MW.

The main reason is that Nautilus, a 1,400 MW interconnector to Belgium, was moved from Suffolk to the Isle of Grain in Kent in November 2024. Even the remaining 352 MW shortfall would not appear until the late 2030s at the earliest. It also depends on other projects going ahead, including LionLink, a proposed link to the Netherlands that hasn’t been approved yet and may be built elsewhere or not at all.

A 2,000 MW subsea cable with converter stations at each end is far too big for a possible 352 MW problem more than a decade away. It also costs over £3 billion and rising, which is paid for through all our electricity bills.

National Grid keeps changing its story

Once the Suffolk argument fell away, National Grid offered new reasons. None of them stand up.

“Government reports say Sea Link is critical.” The 2024 Clean Power 2030 reports said Sea Link was needed to connect two offshore wind farms, Five Estuaries and Rampion 2. The Government has since approved both wind farms without Sea Link. Neither decision letter says Sea Link is required. National Grid took part in both examinations and never argued that it was.

“Ofgem’s early funding proves it’s needed.” Ofgem approved £1.2 billion of early construction funding in November 2025. Ofgem itself has said this approval “is also not a relevant consideration or predeterminant of the DCO approval process.” Using the funding as proof of need is circular reasoning.

“The network needs it to fix bottlenecks.” At the two East Anglian boundaries (EC5 and LE1), there’s no shortfall left once you count the upgrades already planned, such as Norwich to Tilbury and Bramford to Twinstead.

A cheaper alternative that does the whole job

Two overhead line upgrades would solve both problems:

  • Kent: a 400 kV line between Canterbury North and Kemsley for roughly £90 million. Would fix the entire 6,516 MW Kent shortfall and add resilience towards London, where the power is needed. National Grid has already studied this option itself, under the name “CAKE”.

  • Suffolk: a 400 kV double-circuit between Sizewell and Bramford, about 55 km, for roughly £170 million.

That comes to around £260 million against more than £3 billion. It meets the safety rules and links up with upgrades already planned.

Other measures could help further. These include reconductoring existing lines to carry more power, intertrip services, battery storage, and running interconnectors to export when Britain has surplus power.

NESO’s own Summer Outlook (April 2026) points to growing periods of surplus generation, not shortage.

A process that raises questions

  • National Grid signed major supply contracts in December 2025, while the independent examination was still running. That looked like it took the outcome for granted.

  • Big changes such as the Nautilus move weren’t reflected in a revised need case.

  • National Grid companies are behind several linked projects, if they go ahead at all.

Sea Link cost

£3B+

And rising — via electricity bills

Alternative cost

~£260M

Two overhead lines

Claimed problem

1,852 MW

National Grid figure

Actual problem

352 MW

Without speculation

Sizewell group deficit

The claimed 1,852 MW shortage collapses to just 352 MW

National Grid's figure includes projects that have since relocated or remain unapproved. Remove them and the real remaining problem is tiny — and won't arrive until the late 2030s at the earliest.

National Grid's claimed deficit Removed: Nautilus relocated + LionLink unconsented Actual remaining deficit
Claimed: 1,852 MW. Removed: 1,500 MW. Actual: 352 MW.
Sea Link is sized at 2,000 MW — nearly six times the real remaining problem of 352 MW. Even that smaller figure only materialises if several other unapproved projects all proceed.

SC2 boundary deficit — the full picture

The 6,516 MW Kent deficit is already covered by existing tools

Adding up flexible interconnectors, battery storage and grid management services already in place produces a net surplus — without building anything new.

SC2 deficit (6,516 MW) Interconnectors — flex export/import (5,720 MW) Battery storage (2,531 MW) CMIS intertrip service (900+ MW)
SC2 deficit: 6,516 MW. Interconnectors: 5,720 MW. Storage: 2,531 MW. CMIS: 900 MW. Net surplus: ~2,635 MW.
Combined mitigations total ~9,151 MW — exceeding the 6,516 MW deficit by over 2,600 MW. Interconnectors alone can switch from importing to exporting electricity at no extra cost, turning a bottleneck into a surplus.

Existing network capacity

Current capacity already meets all future scenarios

East Anglia EC5 has no persistent shortfall after 2030. South East capacity meets all Future Energy Scenarios — without Sea Link.

East Anglia EC5: 3.3–3.8 GW South East: 3.8–10.2 GW
East Anglia EC5: 3.3–3.8 GW. South East: 3.8–10.2 GW. Both sufficient without Sea Link.

Already-approved upgrades (Tilbury–Grain TKRE)

Planned 2028 upgrades resolve all thermal problems

The approved TKRE upgrade lifts pre-fault capacity to 8–9 GW and keeps the post-fault figure within official safety limits — without Sea Link.

Current (~6.7 GW) After TKRE 2028 pre-fault (8–9 GW) Post-fault safety limit (6.7 GW)
Current: 6.7 GW. TKRE 2028: 8–9 GW. Safety limit: 6.7 GW.

Cost comparison

Sea Link vs the two-line alternative

Two overhead lines cost less than 10% of Sea Link — and fully fix the problem, which Sea Link cannot.

Sea Link (£3,000M+) Two overhead lines (~£260M)
Sea Link: £3,000M+. Alternative: £260M.

Kent SC2 — what Sea Link actually fixes

Sea Link only covers a third of Kent's real problem

SC2 shortfall is 6,516 MW. Sea Link provides 2,000 MW — leaving 4,516 MW still unsolved. A 29 km overhead line fixes all of it for ~£90M.

SC2 total deficit Sea Link fixes Gap left unsolved Canterbury–Kemsley fixes all
SC2: 6,516 MW. Sea Link: 2,000 MW. Gap: 4,516 MW. Canterbury–Kemsley: 6,516 MW.
Sea Link leaves over two-thirds of Kent's problem unsolved and would need costly further work. The Canterbury–Kemsley line at ~£90M resolves it entirely.

The better alternative — full cost breakdown

Two simple overhead lines do the whole job for ~£260 million

A new 400 kV line from Sizewell to Bramford (55 km, ~£170M) resolves Suffolk. A new 400 kV line from Canterbury North to Kemsley (29 km, ~£90M) fully fixes Kent's SC2 boundary — something Sea Link, at more than eleven times the cost, cannot achieve on its own.

Sizewell–Bramford (fixes Suffolk) Canterbury–Kemsley (fully fixes Kent) Sea Link (Kent still 4,516 MW short)
Sizewell–Bramford: £170M — fixes Suffolk. Canterbury–Kemsley: £90M — fully fixes Kent. Sea Link: £3,000M+ — Kent still 4,516 MW short.
Total alternative: ~£260 million. Sea Link: over £3,000 million and rising. The alternatives meet every safety standard, cause far less damage to Minster Marshes and the Kent coast, and can be delivered just as quickly.

Data sources: National Grid APP-320 Strategic Options Back Check Report (March 2025) · NESO Electricity Ten Year Statement ETYS 2024 (January 2025) · NESO Future Energy Scenarios FES 2024 · Ofgem early construction funding decision (November 2025) · Sea Link Development Consent Order, approved 30 October 2026.